[ARCHIVED] Update on Street Construction

Project Updates:

  • East Street: The intersection of East Street and Garfield Avenue should be open by the end of the current week. A rock base is being placed on East Street between Garfield and Washington Place this week. Once the rock base is in place, asphalt will follow.  
  • 10th Avenue: Progress continues, sidewalk removal and replacement will be performed soon.
  • 6th Avenue & West Street: The underground work at the intersection of 6th & West will be complete this week. Reconfiguration of the intersection will start next. All lanes on West Street between 4th and 5th Avenues, including the intersection at 5th, will be open by the end of the week. West Street between 5th and 6th Avenues will remain as two-way traffic with the intersection at 6th Avenue remaining closed.