Work on Jordan Well 10: The new drill rig has arrived at the site for the well near the water treatment plant and has been drilling all week. The well is currently about 240 feet deep and the casing that stabilizes the upper 200 feet of the bore hole has been installed.
Raw Water Main: Water main installation is progressing east of the railroad tracks on 1st Avenue. Con-Struct is currently working at State Street and 1st Avenue. Road closures in affected areas will continue as work progresses, residences affected will be notified.
New nanofiltration water plant: Design for the water plant is complete and the contract for construction of the plant has been awarded to WRH, Inc. of Amana, Iowa. Construction of the plant can begin after the new well is complete. We are expecting the plant to be in operation in the fall of 2026, with a final completion date in the spring of 2027.
Garfield Avenue water main: Work on the replacement of the Garfield Avenue water main between Main and Broad Streets is complete. The contractor will return to seed a few areas in the spring.
New water tower: Construction of the water tower is tentatively scheduled to begin in spring of 2025, with estimated completion in fall of 2026.